Project Milestones

Approved Douglasville Concept Report

Approved Environmental Document

Approved Mitigation Plan

Douglasville Notice of Location & Design Approval

Approved Right of Way Plan

Approved Final Plan

 

Project Plan Development Process

Concept:
Completed 05/21/2010

Environmental: Completed 03/31/2011

Preliminary Plans: Completed 05/27/2011

Right-of-Way Plans: Approved 06/27/2011

Right-of-Way Acquisition:
Completed
Winter 2013

Enviromental
Re-evaluation:

Approved 8/14/2014

Final Plan:
Completed
February 2014

Construction:
10/15/14 to 5/31/2020

 

Conceptual Layouts

Douglasville Layout

Updated Douglasville Layout

Paulding Layout

SR 92 Projects Location Map

Douglasville Project Location Map

Project Description

Conceptual Renderings

Updated SR 92 Realignment

Douglasville Railroad Closure Plan

Brown Street Area - Looking North from US78

Fulgham Drive Area - Looking South from Strickland St.

Hospital Drive Area - Looking North from I-20

Brown Street Existing

Brown Street Proposed

 

FAQ & Comment Forms

Local Contacts

Michelle Wright, Planning Director
6695 Church St.
Douglasville, GA 30134
Ph: 770-920-3000
Fax: 678-449-3053
E-mail

GDOT Contact

Peter Emmanuel, Project Manager
600 West Peachtree St., NW
Atlanta, GA 30308
Ph: 404-631-1158
Fax: 404-631-1588
E-mail

Construction Contacts

Dale Ferris,
Area III Engineer
4125 Roosevelt Hwy. College Park,
GA 30349
Ph: 404-559-6699
E-mail

Nathaniel Counts,
Project Manager
P.O. Box Drawer 970 Marietta, GA 30061
Ph: 770-422-7520
E-mail

 

Douglasville Highway 92 Project

Weekly Construction Update
Phase I, II, & III Construction Awarded to
C.W. Matthews Contracting Co., Inc.

SR 92 Construction Update - Stage 1 Detour

Latest Project Layouts
SR 92 Detour
SR 92 Layout 1
SR 92 Layout 2
SR 92 Transportation Management Plan 1
SR 92 Transportation Management Plan 2

Project Identification Numbers:
CSSTP-0006-00(900), CSSTP-0006-00(901), STP00-0186-01(011), Douglas County P.I. Nos. 0006900, 0006901, 720970.


Douglas County Phase I, II, & III Displays & Detour Layouts

SR92 LAYOUT 1
SR92 LAYOUT 2
SR92 LAYOUT 3
DETOUR 1
DETOUR 2

View the Douglasville SR 92 Groundbreaking Ceremony
Online at MY CITI TV

Full-version Video (1hr25m58s)
Condensed Video (4m35s)


Relocation of SR 92

CSSTP-0006-00(900) Phase 1 – Relocation of SR 92 from Relocated Cooper Street to Relocated Ellis Street including the Construction of Bridge Underpass, and RR Crossing Closures.


CSSTP-0006-00(901) Phase 2 – Relocation of SR 92 from Pine Drive to Relocated Cooper Street.


STP00-0186-00(011) Phase 3 – Relocation of SR 92 from Relocated Ellis Street to north of Malone Road.

Widening of SR 92
CSSTP-0007-00(691) Phase 4 - Widening of SR 92 from Malone Road to Nebo Road.

 


Please check out the video below detailing Georgia Highway 92!

Slide Show of Douglas County Fly-Over